I get asked this a lot lately, so let me give the honest version instead of the reassuring one.
Yes, there's a real risk here — but it isn't "too much supply," which is what most of the coverage keeps repeating. It's the growing distance between what's announced and what's actually built on schedule. And right now that distance is wider than most buyers realise.
Start with the numbers. Dubai delivered 24,800 units in H1 2026 — 18,900 apartments, 5,900 villas and townhouses — up 37.6% year-on-year, according to Cavendish Maxwell's July data. That's the figure everyone quotes. Here's what doesn't make the press release: only 41.3% of what was scheduled for H1 2026 actually got completed in H1. Nearly six out of ten announced completions slipped to later.
The 2027 gap is wider still
Zoom out to 2027 and it gets wider still. 162,500 units are scheduled. Cushman & Wakefield's realistic estimate for what actually delivers is 60,000 — about a third. Of the roughly 525,000 units announced market-wide, only 186,000 have gotten past 20% construction. Most of what's been marketed is, honestly, still a plan on paper.
2027 pipeline: scheduled vs. realistic delivery
Source: Cushman & Wakefield, cited in Truhauz's 2026–27 handover-wave analysis.
A second factor, stacking on top
And now there's a second factor stacking on top of it — one I didn't expect to be writing about a year ago. Since the Strait of Hormuz closure in March, supplier delivery times in the UAE have lengthened. Ordinary building materials are being rerouted around longer, less predictable shipping paths. Nobody's put a hard percentage on it yet, and I won't pretend there is one. But the mechanism is simple: longer routes cost more, and that cost doesn't disappear — a supplier absorbs it, a contractor absorbs it, or it lands in your unit's final price and your handover date. For a market that was already missing nearly 60% of its own schedule before this started, that's not a small thing to stack on top.
You can't take a marketed handover date at face value — and right now, less than ever.
None of this means don't buy off-plan. Escrow still protects your capital regardless, and that hasn't changed. What's changed is that you can't take a marketed handover date at face value — and right now, less than ever.
Three things I'd actually do before signing
Ask for this specific project's construction progress today — a percentage, not the brochure timeline and not the developer's overall reputation.
Ask directly whether materials for this project move through routes affected by the Hormuz disruption. Most sales teams won't volunteer it, but they'll answer if you ask plainly.
Treat the marketed handover date as a floor, not a target, and build your own finances — and any payment plan tied to handover — around it slipping further.
That's the habit I carried over from banking: I don't ask "is this a good project." I ask what's actually been verified versus what's been announced. With everything happening in the region right now, that gap matters more than it has in years.
General information, not financial advice.